Wastewater Treatment Plant Upgrades - Page last updated June 8, 2023.


Click on the image below to view the complete preliminary plan for Phase 2 upgrades to the Wastewater (sewer) Treatment Plant.Salem WWTF Ph2 FP 07-11-22

Project Budget
Total Estimated Costs -                                                                                  $9,500,000
Grants received to reduce costs to citizens                                                      -5,000,000   
          (MO Dept of Natural Resources, American Rescue Plan Act Funding)
Remaining balance to be financed                                                           $4,600,000
         (includes additional $100K for inflation and increased construction costs)
Ballot question on 4/4/23 election to finance balance via Revenue Bond was passed by the Voters of Salem.



Timeline Details for the Wastewater Treatment Plant
  • 2004 - Spring Creek was placed on EPA’s 303d list of impaired waters. 
  • 2010 - Total Maximum Daily Load (TMDL) study of contaminants was completed on the stream.
  • April 2022 - TMDL Study was updated and new levels for discharge to the stream were set by the Environmental Protection Agency (EPA).
  • The City of Salem has been working with the Missouri Department of Natural Resources (MDNR) continually during this time to develop a reasonable and affordable solution to meet the new TMDL levels.
  • Completed - Phases 1 A and B of upgrades to the wastewater treatment plant.
  • Submitted – Wastewater Treatment Facility (WWTF) Plan for future upgrades to MDNR detailing a phased improvement plan to meet the new TMDLs.
  • Estimated Cost of new WWTF upgrades - $9,500,000
  • November 2022 – City of Salem awarded MDNR ARPA Grant for upgrades of $5,000,000 – Funds must be spent by December 31, 2026
  • March 2023 – City of Salem to apply for MDNR State Revolving Fund (SRF) grant of $2,000,000
  • April 2023 – Sewer Bond in the amount of $4,600,000 was approved by voters on ballot during municipal election.
  • Spring 2023 – Application to MO Department of Economic Development for a Community Development Block Grant (CDBG) for $750,000
  • Bond financing is lower cost than traditional financing.
  • IF THE BOND PASSES –$2,000,000 SRF grant is almost guaranteed
  • IF THE BOND PASSES AND WE GET THE CDBG GRANT OF $750,000 –The Bond will close at about $1,800,000 instead of $4,600,000
  • WITH THE IFS IN THE ABOVE LINE – $9,500,000 – 5,000,000-2,000,000-750,000 = $1,750,000. This amount to be financed through the bond funding and payback will be through increased sewer rates
  • Sewer Bond is anticipated to close Fall of 2024.
  • In the meantime, City Staff are continuing to look for and vet additional funding sources to potentially reduce the amount of the bond (future liability) even further.

#Keep Current.
 .
 .
Sign Up for Notifications